9. ENTRY MARKER
Construction was substantially completed in 2018 on the new limestone entry marker — with new gathering plaza and lighting — at the Wells/Skinker entry to the Park. Landscaping will be completed in 2019.
10. LIBERAL ARTS BRIDGE & MUNY TRIBUTARY
For this $3.1 M project, the new bridge opened in January 2018, with the new path extension, meadow and waterway improvements taking shape in spring and summer. Project included 35,000 native plantings, 69 new trees and 4,000 tons of rocks and boulders.
11. CENTRAL FIELDS
This $5.8M project — improved fields for soccer, rugby and large comunity events, new facilities, new irrigation and drainage systems, and more — was substantially completed in 2018. Turf has been growing in. Stay tuned for an exciting announcement about the reopening of the fields in 2019.
12. BOEING AVIATION FIELDS
Broke ground on this $3.3 million project — lighting and irrigating all remaining fields, improving paths and visitor access — in fall 2018. Look for the fields to reopen this fall.